Questions
Permits, snow, delivery and price
What our clients in Kosovo ask most often before ordering a steel building, a cabin or a pavilion.
Building permit
Do I need a building permit?
Yes, for every permanent building. The municipality issues it. A single-storey warehouse is usually Category I; workshops, factories and agricultural buildings (barns, stables) are Category II, with a fuller file.
How long does the permit take?
The law sets 15–30 days for the building conditions and 30–45 days for the permit. In practice allow 2–4 months, sometimes longer. That is why we start the file as soon as you approve the design, in parallel with fabrication.
Who signs the design?
The factory's calculations are adapted and signed by a Kosovo-licensed structural engineer, who takes professional responsibility. A licensed fire designer prepares the fire-protection report. We coordinate both.
What are the municipal fees?
In Prishtinë the 2016 regulation sets a €6.50/m² permit fee and a €12/m² infrastructure charge in the urban zone. Other municipalities have their own rates. These are paid to the municipality and are not in our price; we confirm them for your site.
Design and loads
Which standards is the building designed to?
Eurocode: EN 1990/1991 for loads and EN 1993 for steel, with snow, wind and seismic values for your site. Fabrication to EN 1090, panels to EN 14509. We ask for the factory's certificates and check them before ordering.
How much snow does the roof carry?
As much as your site needs. For Prishtinë we design for at least 1.2–1.5 kN/m² ground snow, above about 800 m for 2.0 kN/m² or more, and for Pejë, Prizren and the mountains with a site calculation to EN 1991-1-3. The engineer sets the final value. Many standard buildings from China arrive designed for 0.5 kN/m²; we do not accept that.
Can the roof carry solar panels?
Yes. Choose a solar-ready roof in the configurator and the purlins are sized for the panel load. Panels, inverters and batteries come from our sister company Meridian Volta.
Fire and panels
Which panel should I choose?
EPS is the cheapest, PU/PIR insulates better for the same thickness, and rock wool is non-combustible (class A2) and is often required for cold stores, large warehouses or by the insurer. We ask for fire classes to EN 13501-1, not Chinese grades.
Who approves the fire protection?
The Emergency Management Agency (AME) gives consent twice, for the building conditions and for the main design, and inspects at the end with the building inspector. The panel type is decided with the fire designer before the final quote.
Delivery and erection
How does the building arrive from China?
In 40' containers to the port of Durrës (or Thessaloniki), then by truck to your site. Long rafters are split into segments of about 10 m with bolted splices. A 30 × 60 m warehouse with 100 mm panels takes about 9 containers.
How long does it all take?
Typically 15–21 weeks from signed order to handover: design and engineering 3–5 weeks, fabrication 4–6 weeks, sea and road 5–6 weeks, erection 2–6 weeks. December shipping is often slower and dearer. Your dates are confirmed in the quote.
Who erects it?
A local erection crew with a crane, working to the erection drawings, with technical supervision where the building needs it. You can choose full erection, supervision only or supply only.
Who builds the foundations?
A local contractor, to the engineer's drawings. We send the anchor bolts and the setting-out plan, and the foundations are built while the steel is at sea.
Price
How accurate is the configurator estimate?
It is an indicative range, ex VAT, for planning. The binding price is in our quote, after the structural design and at current steel and freight prices.
What is not included?
Foundations and floor slab (usually €50–80/m²), municipal permit charges, utility connections and VAT at 18%. The quote lists exactly what is included.
Can I extend the building later?
Yes. Portal-frame buildings extend easily in length; tell us at design stage and the end frame is designed to take the extension.
Cabins and restaurants
Are the cabins fit for a Kosovo winter?
Yes, with the winter package: at least 150 mm rock wool or PIR in walls and roof, thermal breaks, double or triple glazing and a roof designed for 2.0 kN/m² snow. For expandable container homes, at least 75–100 mm rock wool.
What permits does a restaurant or café need?
A municipal permit (building or temporary structure, depending on the case) and food-premises registration with the Food and Veterinary Agency (AUV). We prepare the drawings each one needs.
Something else? Write to info@meridianprefab.com or request a quote.
General information, not legal advice. Fees and procedures are confirmed for your site and municipality · updated November 2026